This guide explains how to structure the employer’s requirements for a hybrid power plant EPC tender: what to specify and what to leave to the contractor, where the scope boundaries fall, how to describe performance and controls, and which mistakes lead to variations and delays once construction starts.
What the employer’s requirements do
In most EPC forms the employer’s requirements are the part of the contract that defines the purpose, scope and design standards of the works. The contractor’s proposal responds to them, and on award both become contract documents. If the plant fails to meet the requirements, the contractor must correct it; if the requirements were wrong or incomplete, the cost usually falls back on the employer.
For a single-technology plant this document is already long. For a hybrid plant it must also explain how the parts work together, which is where most of the drafting effort should go.
Functional or prescriptive specification
A functional specification states outcomes: firm capacity at the point of connection, energy delivered per year, availability and response times. A prescriptive specification states equipment: module type, inverter rating, battery chemistry or engine model. Pure functional documents give the contractor freedom to optimise but make bids harder to compare; pure prescriptive ones move design risk back to the employer.
Most successful hybrid tenders mix the two. They specify outcomes for the plant as a whole and set minimum standards for key equipment, such as approved manufacturer lists, design life and warranty terms, while letting bidders propose the configuration that meets the outcome at the lowest lifetime cost.
Drawing the scope boundaries
Every component needs an owner. The document should state clearly whether the contractor supplies the solar field, wind turbines, battery system, thermal units, substation, transmission line, control building, water supply, roads and site camp, and which of these are supplied by the employer or others.
Where the employer supplies something, such as an existing thermal station or a utility-built line, the requirements must give its technical data and state the terminal point. A short scope matrix, listing each item against supply, install, test and commission responsibilities, prevents the gaps that otherwise appear between packages. Thermal firming units deserve the same care, and our page on delivering complete power station scopes shows how thermal and renewable parts can sit under one contract.
Design basis and site data
Bidders need the same site data to produce comparable designs. That includes solar resource and wind data with their sources, geotechnical and topographic surveys, flood levels, ambient temperature extremes, dust conditions, altitude and seismic zone. Where data is incomplete, the document should say who carries the risk of what is later found.
Investing in site studies before the tender reduces that risk for everyone. Our article on site investigations before notice to proceed covers which studies should be completed before contracts are signed.
Performance and availability requirements
For a hybrid plant the key performance figures are usually firm or dispatchable capacity, annual energy or renewable fraction, fuel consumption of the thermal units, battery round-trip efficiency and plant availability. Each figure needs a definition, a measurement point, reference conditions and a test method.
Linking each guarantee to a remedy, such as performance damages or a right to require correction, belongs in the commercial terms. Our explanation of liquidated damages in renewable contracts shows how technical figures and commercial remedies must be drafted together.
The hybrid control system
The plant controller decides how solar, wind, battery and thermal units share the load, so its functions must be described in operational terms: how spinning reserve is maintained, how the battery is charged and discharged, when thermal units start and stop, how ramp rates are limited and what happens when communication is lost.
The requirements should also say who owns the control software, how settings can be changed after handover, which data the employer can access and how cyber security will be managed. Vague wording here produces a plant that works at acceptance but cannot be tuned later.
Grid connection and studies
If the plant connects to a utility network, the grid code and the connection agreement set technical limits on voltage range, reactive capability, ride-through during faults and the response to frequency changes. The employer’s requirements should name the applicable code, attach the connection offer and state who performs and pays for grid studies and compliance testing.
For an island plant at a mine or industrial site, the equivalent requirements cover frequency stability, motor starting and protection coordination with the existing network.
Interfaces, quality and documentation
Hybrid plants have more interfaces than most projects: between technologies, between contractors, and with existing assets. The document should list every interface, the information each party must provide and the dates by which it is needed.
Quality requirements, design review steps, document formats and the as-built package should be specified rather than left to the contractor’s standard practice. Owners often appoint an owner’s engineer for the hybrid project to review submissions against the requirements during design and construction.
Testing, acceptance and handover
The requirements should define the sequence from component tests through system tests to the plant performance and reliability tests, with clear pass criteria and retest rules. Hybrid control functions need their own acceptance tests, ideally including simulated cloud events and unit trips.
Handover requirements should include training, spares, special tools, software licences and warranty arrangements, together with the O&M manuals. A plant that passes its tests but arrives without these is not ready for operation.
About the authors
This guide comes from the USP&E project engineers and contract managers who prepare and deliver renewable and hybrid power plant EPC contracts. USP&E is an EPC and O&M contractor, not a broker, with 150+ power projects in 45+ countries, 25,000 MW contracted since 2002 and 24+ years in the field. Our work on combined solar, storage and thermal plants covers the full route from tender scope to commercial operation.
Offices: Colorado Springs (1755 Telstar Dr, Suite 300), Knoxville (800 S Gay St, Suite 700), London (162-168 Regent Street), Johannesburg (22 Kildoon Rd, Bryanston), Cape Town (31 Brickfield Road, Woodstock) and China (No. 1 Ningzhou Road, Wuxi). Regions: USA | AFRICA | UK | UAE | CHINA. ISO 9001 and ISO 45001 certified.
Hybrid EPC tender questions
What are the employer’s requirements in an EPC contract?
They are the contract document that defines the purpose, scope, design standards and performance of the works the contractor must deliver.
Should a hybrid EPC tender be functional or prescriptive?
Usually a mix: outcomes for the whole plant, plus minimum standards for key equipment such as approved makers, design life and warranties.
Who should carry site data risk in a renewable EPC tender?
It depends on the contract, but the employer usually carries the risk of data it supplied, which is why early site studies matter.
What should the hybrid control system section cover?
How units share load, how reserve is held, how the battery operates, ramp limits, loss-of-communication behaviour and software ownership.
Why do hybrid EPC projects lead to variations?
Most often because scope boundaries, interfaces or performance definitions in the tender documents were unclear.
What should the contractor hand over when a hybrid EPC contract ends?
Training, spares, special tools, software licences, warranties, O&M manuals and the as-built documents.