This guide explains what a wind farm BOP EPC contract normally includes, where the main risks sit, and how the interface with the turbine supplier should be managed so that neither side is left waiting for the other.
What balance of plant means on a wind project
In most wind farm contracting models, the turbine supplier delivers, erects and commissions the turbines under a turbine supply agreement. Everything else needed to make the site work is the balance of plant. A BOP EPC contractor takes responsibility for designing and building that remainder as one package.
- Site access, internal roads and drainage.
- Crane hardstands, laydown areas and blade storage pads.
- Turbine foundations, including anchor cages or bolt assemblies supplied to the turbine maker’s design.
- The medium-voltage collection cable network linking the turbines.
- The project substation and, depending on the deal, the connection line to the grid.
- The operations building, SCADA communications network and permanent met masts.
Roads and crane hardstands
Wind components are long, tall and heavy. Blade transport sets the minimum bend radii, clear widths and swept paths on every road, while nacelle and tower loads set the pavement design and the bearing capacity of crane hardstands. Gradients matter too; steep sections may need towing assistance or a different road alignment.
Roads and hardstands are usually on the critical path, because turbine deliveries cannot start until they are finished and tested. Plate load tests or similar checks on hardstands, carried out before cranes arrive, prevent expensive standby time. Good drainage design keeps the roads usable through the wet season, when many delays start.
Turbine foundations
Foundation type depends on ground conditions. Spread gravity foundations are common where soils are adequate; piled foundations or rock anchors are used where they are not. The design loads come from the turbine supplier, so the foundation designer depends on early, accurate load documents and on the geotechnical work described in our post on site investigations before notice to proceed.
Each foundation is a large single concrete pour with tight tolerances on the embedded anchor assembly, because a few millimetres of error at the top flange becomes a tower out of plumb. Concrete supply, temperature control during curing and inspection hold points all need planning, particularly on remote sites where batching plants are set up specially for the project.
The collection system
Turbines are linked by buried medium-voltage cables, usually arranged in radial strings or rings that feed back to the substation. String design trades cable cost against losses and against how much generation is lost when one cable fails. Ring arrangements cost more but let part of a string keep running after a fault.
Cable routes, trench design, thermal backfill, joints and earthing all need careful quality control. Cable faults found after energisation are slow to locate and repair. Testing at installation and before energisation, recorded in the inspection and test plan, is the main defence; our article on inspection test plans and punch lists covers how that evidence is kept.
Substation and grid connection
The substation steps the collection voltage up to the grid voltage and contains the protection, metering and control equipment the grid operator requires. Long-lead items such as power transformers and high-voltage switchgear often set the earliest possible energisation date, so they are ordered early, sometimes before full notice to proceed.
The grid connection itself may be built by the BOP contractor, by the network operator, or split between them. The boundary needs to be fixed in the contract with the same care as the turbine interface. Our page on substation and line scope goes into the electrical items in more depth.
SCADA, communications and met masts
Each turbine has its own controller, but the wind farm also needs a site SCADA system, a fibre or radio network back to the substation, and a power plant controller that meets the grid code for voltage, reactive power and curtailment instructions. Permanent met masts or remote sensing devices support power curve testing and performance reporting.
Responsibility for SCADA is often divided between the turbine supplier and the BOP contractor. A written split covering hardware, software, cyber security and testing avoids gaps where each party assumes the other will deliver.
Managing the interface with the turbine supplier
The biggest single risk in a split contract model is the interface between the BOP contractor and the turbine supplier. Foundation loads, anchor assembly delivery, hardstand handover, cable termination in the tower and the first back-feed power to each turbine are all hand-off points with dates attached.
A detailed interface matrix, signed by both parties and the owner, should list every hand-off, its acceptance criteria and its date. Weekly joint progress meetings during construction keep it current. When dates slip, the matrix shows who caused the slip, which is far easier than arguing it out later under the payment terms described in our post on renewable EPC payment milestones.
Weather and programme risk
Wind farms are, by definition, built on windy sites. Crane lifts of blades and nacelles have wind speed limits, and long periods above those limits can stop erection for days. Concrete pours face their own temperature limits. A realistic programme carries weather allowances based on site data rather than a generic figure.
Sequencing foundations well ahead of erection, and keeping several turbine positions ready at once, gives the erection crew somewhere productive to work when one location is blocked.
Split packages or one wrapped contract?
Owners can let separate civil and electrical BOP contracts, a single BOP EPC contract, or a full wrap that also takes responsibility for the turbine supply. More splits can lower the headline price but move interface risk to the owner. A single BOP contractor removes one interface; a full wrap removes nearly all of them at a higher contractor margin.
Lenders usually prefer fewer interfaces, and many will ask the owner to show how any remaining gaps are covered. Where wind is combined with storage or thermal firming, the same logic applies to those packages as well. Our approach to integrated delivery is described on the power plant EPC projects page.
Who wrote this guide
This guide comes from the renewable and hybrid EPC engineers who plan civil, electrical and interface packages for wind, solar and firmed power plants. USP&E is an EPC and O&M contractor, not a broker, with 150+ power projects in 45+ countries, 25,000 MW contracted since 2002 and 24+ years in the field. How we combine renewables with storage and dispatchable plant is explained on our hybrid power systems page.
Offices: Colorado Springs (1755 Telstar Dr, Suite 300), Knoxville (800 S Gay St, Suite 700), London (162-168 Regent Street), Johannesburg (22 Kildoon Rd, Bryanston), Cape Town (31 Brickfield Road, Woodstock) and China (No. 1 Ningzhou Road, Wuxi). Regions: USA | AFRICA | UK | UAE | CHINA. ISO 9001 and ISO 45001 certified.
Wind farm BOP: common questions
What is balance of plant on a wind farm?
Everything except the turbines themselves: roads, crane pads, foundations, the collection cable network, the substation, SCADA communications, met masts and the operations building.
Who designs wind turbine foundations?
Usually the BOP contractor’s designer, using load data from the turbine supplier and site geotechnical results. The turbine supplier normally reviews and accepts the design.
What is usually on the critical path?
Access roads, crane hardstands and the substation’s long-lead transformer and switchgear. Turbine erection cannot start until roads and pads are ready.
Why are ring collection systems used?
A ring lets part of the string keep exporting after a cable fault, reducing lost generation, at a higher cable cost than a simple radial layout.
Is a single BOP contract better than several packages?
It removes interfaces the owner would otherwise manage. Lenders often prefer it, although separate packages can lower headline prices for experienced owners.
How is weather handled in the programme?
With allowances for crane wind limits and concrete temperature limits based on site data, and by keeping several turbine positions ready so work can move.
Talk to us about your wind or hybrid project
Send the site layout, turbine model and grid connection details, and our engineers will outline a balance of plant scope, interface matrix and delivery sequence for your project.
Phone +27 10 822 2324 during office hours, or write to info@uspeglobal.com at any time; the renewable project enquiry page also routes straight to our project engineers. For firming and backup plant, see the current USP&E equipment inventory.
