This guide explains how renewable EPC teams choose the collector voltage, arrange feeders, size cables, estimate losses, earth the system and test it before energisation, so that owners and lenders know what a sound design looks like.
What the collector system includes
The collector system starts at the low voltage to medium voltage transformer beside each inverter station or turbine and ends at the incoming feeder bays of the plant substation. It includes those transformers or their high voltage terminals, ring main units or turbine switchgear, MV cables, joints, terminations, earthing conductors, fibre optic cables and the trenches that carry them.
Defining the boundary clearly matters for the contract. Our article on substation and line scope explains where the collector package typically hands over to the substation package.
Choosing the voltage
Most utility-scale solar and wind plants use a collector voltage between about 22 kV and 36 kV, with 33 kV and 34.5 kV common. Higher voltage carries more power per feeder with lower current and lower losses, but needs more insulation and more expensive switchgear.
Local practice and spares availability also count. Matching the voltage used by the national utility makes transformers, switchgear and cable easier to source and maintain over a 25 year plant life.
Feeder layout: radial or looped
The simplest layout is radial: a string of inverter stations or turbines daisy-chained along a feeder back to the substation. It is cheap, but a cable fault near the substation disconnects every unit beyond it until repair.
Looped or ring arrangements, run normally open, let operators isolate a faulty section and restore the rest of the feeder by switching. They add cable and switchgear cost, so the choice depends on the value of lost energy, repair times at the site and the requirements of the offtaker.
Sizing the cables
Cable size is set by current, short circuit withstand and voltage drop, and then adjusted for installation conditions. Buried cable ratings depend heavily on soil thermal resistivity, burial depth, ambient ground temperature and how closely circuits are grouped in one trench. Dry, sandy soils with high resistivity can reduce ampacity sharply.
Soil thermal tests should be part of the site investigations described in our page on pre-NTP site investigations. Designing with assumed values that turn out optimistic leads to cables running hot and ageing early.
Loss arithmetic
Consider a 33 kV feeder carrying 20 MW at a power factor of 0.95. Current equals power divided by the product of the square root of three, line voltage and power factor: 20 MW over 1.732 times 33 kV times 0.95 gives roughly 368 A. With an aluminium conductor resistance of about 0.13 ohm per km at operating temperature, losses are three times current squared times resistance, close to 53 kW per km, or about 0.26 percent of feeder output for every km at full load.
Because losses rise with the square of current, they fall quickly at part load, so annual energy losses should be calculated against the real generation profile. Comparing a larger conductor’s lower losses with its higher cost over the plant life often justifies upsizing the first sections nearest the substation, where current is highest.
Earthing and fault levels
The MV system is usually earthed at the substation through an earthing transformer or resistor that limits earth fault current. The earthing method sets protection settings and the voltage rating of cable insulation and surge arresters, so it must be decided early.
Every inverter station or turbine needs its own earthing system bonded to the cable screens. Screen bonding arrangements, whether both ends or single point, affect circulating currents and losses on long single-core circuits.
Cable charging and reactive power
Long MV cable networks generate reactive power, especially at night when generation is low. That charging current can push voltage up at the connection point and must be included in the plant’s reactive power balance and the grid code studies.
Inverters can often absorb this reactive power, but at night some plants need reactors or a hybrid controller to manage it. Plants with storage or thermal firming, covered on our hybrid power systems page, must include those assets in the same study.
Trenching, crossings and joints
Trench routes should avoid drainage lines and follow access roads where possible. Road, river and pipeline crossings may need ducts or horizontal directional drilling, and each crossing affects cable rating.
Joints and terminations are the weakest points in any MV network. Use jointing kits matched to the cable, certified jointers, clean working conditions and full records of each joint’s location. GPS records save days when a fault has to be found years later.
Fibre, SCADA and access for O&M
Fibre optic cable for plant SCADA, protection signalling and inverter monitoring normally shares the MV trench, laid in its own duct at a defined separation from the power cables. Planning spare fibres and spare ducts at this stage costs little and avoids reopening trenches when the plant is extended or a storage system is added later.
Think about the operations team as well. Route markers, joint position records, accessible ring main units and clear feeder labelling let technicians isolate and earth a feeder quickly and safely. A collector design that looks efficient on paper but forces long switching trips across the site lengthens every outage.
Testing before energisation
After installation, MV cables are tested for sheath integrity and insulation, commonly with a very low frequency withstand test and, where specified, partial discharge measurement. Ring main units and transformers are tested to their own procedures.
These tests belong in the inspection and test plan, as set out in our guide to quality ITPs and punch lists. Energising a feeder without signed test records shifts risk to the owner that should sit with the contractor.
About the authors
This guide comes from the USP&E electrical design engineers and site managers who deliver renewable and hybrid plants from collector cables to grid connection. USP&E is an EPC and O&M contractor, not a broker, with 150+ power projects in 45+ countries, 25,000 MW contracted since 2002 and 24+ years in the field. Our power plant EPC delivery covers MV networks as part of full plant scope.
Offices: Colorado Springs (1755 Telstar Dr, Suite 300), Knoxville (800 S Gay St, Suite 700), London (162-168 Regent Street), Johannesburg (22 Kildoon Rd, Bryanston), Cape Town (31 Brickfield Road, Woodstock) and China (No. 1 Ningzhou Road, Wuxi). Regions: USA | AFRICA | UK | UAE | CHINA. ISO 9001 and ISO 45001 certified.
Collector system questions
What is a collector system in a solar or wind plant?
It is the medium voltage network of transformers, switchgear, cables and joints that gathers power from inverter stations or turbines and carries it to the plant substation.
What voltage is used for collector systems?
Most utility-scale plants use roughly 22 kV to 36 kV, with 33 kV and 34.5 kV common, matched where practical to local utility practice.
How large are collector system losses?
In the example of a 33 kV feeder carrying 20 MW, losses are about 0.26 percent per km at full load and much lower at part load.
Should feeders be radial or looped?
Radial feeders cost less. Looped feeders let operators restore unfaulted sections by switching, which pays off where repair times are long.
Why does soil matter for MV cable sizing?
Buried cable ratings depend on how well the soil removes heat. Dry, high resistivity soils reduce ampacity, so soil thermal testing is essential.
What tests are done before energising MV cables?
Sheath and insulation tests, usually including a very low frequency withstand test and partial discharge measurement where specified.
Review your collector design
Send your layout, single line diagram and soil data, and our engineers will review feeder arrangement, cable sizing and losses for your renewable project.
Phone +27 10 822 2324 during office hours, or write to info@uspeglobal.com at any time; the project contact form also routes straight to our project engineers. Firming plant for hybrid projects is listed in our power equipment inventory.